Installation

Before delivery, each inverter is strictly checked and tested. To prevent any damage during transport, the case needs to be opened and checked before installation of energy storage inverter. The following should be checked:

  1. Check whether the items in the packing list are consistent with the real objects.
  2. Check whether the data (such as product model, rated capacity and voltage) on the product nameplate is consistent with purchase contract.
  3. Check whether the ex-factory documents and accessories are complete.
  4. Check whether the energy storage inverter is deformed and falls off paint.
ItemQuantityDescription
Inverter1
Latch panel1To fix the inverter to the preinstalled position
Expansion bolt (M12×80)5To fix the latch panel to the preinstalled position
Documents pack 1Including QC certificate, packing list, ex-factory test report
RJ45 connector cap3To protect the RJ45 connector and cable connected
Ф5.5-5 Ring terminal1To fix ground wire
Ф6 cord end terminal6To fix the cable in AC to the wiring terminal
Ф10 cord end terminal6To fix the cable in AC to the wiring terminal
Ф25 cord end terminal4To fix the cable in DC to the wiring terminal
Ф2.5 hex socket wrench1Used to open the panel
M5 bolt2To fix ground wire

Environment requirements

  • The inverter is designed for indoor use. Direct sunshine, rain and ponding should be avoided.
  • The installation environment is clean. The air should not contain lots of dust.
  • The installation should be conducted in a well-ventilated environment so as to ensure good heat dissipation.
  • Air inlet and outlet should not be sheltered so as to make ventilation duct unblocked.
  • Environment temperature should be -20~45℃ so as to ensure that the inverter has the best operation state. Over-high and over-low temperature will shorten the service life of inverter.

Carrier requirements

  • The installation carrier of inverter should be fireproof.
  • Don’t install the inverter on the flammable construction materials.
  • Please ensure that the installation surface is firm and meets the load bearing requirements for inverter installation.
  • Don’t install the inverter onto the wall with poor sound insulation in the residence district so as to prevent any interruption caused by operation noise against the residents in the residence district.

Installation requirements Install the inverter vertically or by backward leaning for 15° so as to facilitate its heat dissipation.